Seawall permits in Charlotte County

Up to three levels of government can have a say over a seawall job here: the county building permit, the state's environmental rules (FDEP) and the Army Corps of Engineers. This guide shows which usually come up and what to ask.

General information, not legal advice. Your contractor and the agencies have the final word.

Which rules a job can touch

Pick your job to see which of these commonly apply. The full list reads as plain text without JavaScript.

Charlotte County

  • Residential seawall permit, with a plan that meets county codeVoid if work hasn't started within 180 days
  • State and federal approvals filed with the countyWhere the work is over state or federal waters

State: FDEP, Fla. Admin. Code 62-330.051

  • (12)(a) Building, replacing or repairing seawalls or riprap in man-made waterwaysExempt, conditions apply
  • (12)(b) Restoring a wall damaged by a discrete event in the last yearNo more than 18 in. waterward of the old wall
  • (12)(c) A wall in wetlands or surface waters between and adjoining existing wallsExempt, conditions apply
  • (12)(d) Batter piles, king piles or a cap used only to stabilize and repair a wallIf they don't impede navigation
  • (5)(b) Private docks, piers and docking facilitiesSize and use conditions apply

Federal

  • U.S. Army Corps of Engineers permitWhere work is in navigable or federal waters

City of Punta Gorda

  • Canal maintenance programAsk first if you're on a city canal

An FDEP exemption is not automatic: each one has conditions in the rule, and work outside them needs a permit. Ask your contractor to show you which rule they're relying on.

The county permit comes first

For a residential seawall in Charlotte County the county building permit is the first step. The application asks for a plan that meets county code, and the state and federal approvals ride along with it.

The plan. The county's residential seawall permit application needs a plan that meets county code. Your contractor normally prepares it; ask who will.

Other approvals. If the work is over state or federal jurisdictional waters, the application also calls for FDEP, Army Corps or other required permits. The county's environmental brochure says all applicable state and federal permits must be submitted to the county.

The 180-day clock. The permit becomes void if work hasn't started within 180 days. Fix the start date with the contractor before the permit is pulled.

Commercial walls. The county lists possible FDEP and/or Army Corps approval for commercial seawalls. We haven't confirmed county fee amounts or inspection steps, so ask the county building department.

The five FDEP exemptions people ask about

Florida's rule 62-330.051 lists activities exempt from an environmental resource permit. These five come up most for Charlotte County waterfront owners. The wording below is quoted or closely paraphrased; the rule itself, at Cornell LII, is the reference.

  • (12)(a) "Construction, replacement, and repair of seawalls or riprap in artificially created waterways." Exempt, subject to conditions.
  • (12)(b) Restoring a seawall or riprap where the damage or destruction happened within the last year from a discrete event, and the restoration is no more than 18 inches waterward of the prior location.
  • (12)(c) A seawall or riprap built in wetlands or surface waters between and adjoining existing walls.
  • (12)(d) Installing batter piles, king piles, or a seawall cap "used exclusively to stabilize and repair seawalls", provided they do not impede navigation.
  • (5)(b) Private docks, piers and docking facilities. Conditions on size and use apply.

An exemption is not automatic. Work outside an item's conditions needs a permit, and the conditions are in the rule, not in this summary.

Confirm with FDEP's district office or the Southwest Florida Water Management District (SWFWMD), or ask your contractor to name the exact rule and show the conditions are met. An exemption from the state permit does not remove the county permit or an Army Corps permit.

A worked example: a public job

Charlotte County's page for the Bayshore Live Oak Park seawall replacement in Port Charlotte describes a U.S. Army Corps of Engineers permit, followed by FDEP and SWFWMD approvals. A private wall may need fewer approvals, but the path shows who answers which question.

Ask each of them about your own address. We can't tell you what yours needs.

Who answers what

  • County building departmentcounty permit
  • FDEP district office or SWFWMDexemptions
  • U.S. Army Corps of Engineersfederal waters
  • City of Punta Gorda Public Workscanal program
  • Your contractorwho pulls each

Written into the quotewho pulls what

Not sure which rules apply? Describe the wall and ask the contractors.